Project Overview
Tekno Karya Mandiri was engaged to manage and engineer a multi-story commercial office development with strict performance, quality, and timeline requirements.
Scope of Work
- • Construction management and coordination
- • MEP engineering design and integration
- • Quality assurance and technical compliance
- • Schedule and cost control
Project Objectives
- • Deliver the project within an 18-month schedule
- • Ensure system reliability above 99%
- • Optimize energy efficiency and lifecycle cost
- • Maintain strict safety and compliance standards
Engineering & Delivery Methodology
Planning & Design
- • Engineering analysis and BIM coordination
- • Value engineering and system optimization
Execution
- • Integrated construction & MEP coordination
- • On-site quality and safety supervision
Testing & Commissioning
- • System testing and performance verification
- • Operational readiness validation
Project Timeline
Engineering & Design
Duration: 4 Months
Januari - April 2023
Construction
Duration: 10 Months
Mei 2023 - Februari 2024
Testing & Commissioning
Duration: 3 Months
Maret - Mei 2024
Handover
Duration: 1 Month
Juni - Juni 2024
Challenges & Solutions
Challenges
- • Complex MEP coordination in limited vertical space
- • Tight construction schedule
- • High operational reliability expectations
Solutions
- • Early-stage interdisciplinary coordination
- • Phased construction strategy
- • Strict quality checkpoints
Key Outcomes
97%
Schedule Accuracy
99.2%
System Reliability
18%
Energy Efficiency Gain
Standards & Compliance
- • ISO 9001 Quality Management
- • SNI & IEC Electrical Standards
- • Local building & safety regulations